Blog

Architecture

Cliff House Construction Update (concrete pillars, grade beam prep)

The concrete pillars have been in place.

 

The rebars are going to be embedded into the grade beams.

 

The rebar / form work for the grade beams are taken place.


Ranch House Construction Update (concrete driveway completion)

The concrete has been installed.  The concrete is 4,500 PSI, with 10% fly ash content.  (deep broom finish)

 

The expansion joints will be sealed with polyurethane elastomeric sealant.

 

 


Ranch House Construction Update (driveway concrete forms / rebars)

We worked on concrete forms & rebars for a new driveway.  The Fire Department requires a driveway to be accessible with emergency vehicle, thus it shall be able to handle 75,000 lbs.

Besides, we still need to bring in a Super 10 dump truck, etc to deliver materials to the site, so we went with 6″ slab with #4 bars @ 18″ O.C. each way.


1 2 3 5